This is the link that got severed - BD's only line: SEA-ME-WE-4. Redundancy on the line would not cut it. BD apparently is trying to get SEA-ME-WE-5 as well.



Apparently we built it! "The SEA-ME-WE 4 cable system was developed by a consortium of 16 telecommunications companies which agreed to construct the project on 27 March 2004.[2] Construction of the system was carried out by Alcatel Submarine Networks (now Alcatel-Lucent Submarine Networks, a division of Alcatel-Lucent) and Fujitsu.[2] The eighteen month construction project was completed on 13 December 2005 with a cost estimate of US$500 million.[2][4] Segment 1 construction, running 8,000 kilometres from Singapore to India, was done by Fujitsu, which also provided the submarine repeater equipment for Segment 4.[4]" - wiki